How to Calculate Mortar for a Brick Wall in 5 Steps
Measure the wall, divide by 100, multiply by bags per 100 sq ft, add waste, and order. This guide works the 20 ft by 8 ft example step by step — 160 sq ft, 4.8 bags exact, 6 bags with 10% waste — so the merchant trip is settled before the first course is laid. For the interactive version, use the mortar calculator.
Mortar for a brick wall in one line
Mortar for a brick wall is wall area, divided by 100, times bags per 100 sq ft, plus waste. A 20 ft by 8 ft wall is 160 square feet; at 3 bags per 100 sq ft that is 4.8 bags exact, and with 10% waste the order is 6 bags. The rest of this guide is about getting those three inputs honest: the wall size, the bags per 100 sq ft, and the waste allowance.
Step 1: Measure the wall face
Measure the length and the height of the wall face in feet, edge to edge, on the face itself — not the footing, since the mortar count follows the face area, and a wall face is what the bricks cover. The worked example is 20 ft long and 8 ft high, a normal garden wall. Walk the tape along the face, not around the back, and if the wall has a door or window opening, measure that opening too: it comes off the area in step two, since an opening is wall that is never mortared. A wall that is 20 ft by 8 ft has an area of 160 square feet, and that one number is the foundation of everything that follows.
Step 2: Divide the area by 100
Mortar is rated by the hundred square feet, so divide the wall area by 100: 160 divided by 100 is 1.6 hundreds of square feet. This division is the step that turns a measurement into a bag rate, and it is where openings are subtracted: a 20 ft by 8 ft wall with a 3 ft by 7 ft door is 160 minus 21, or 139 square feet, which is 1.39 hundreds. Keep the decimal — it is not rounded away, since a fraction of a hundred square feet is still a fraction of a bag.
Step 3: Multiply by bags per 100 sq ft
Multiply the hundreds by the bags per 100 sq ft from the bag label. A standard brick wall takes 3 bags per 100 sq ft, so 1.6 hundreds times 3 is 4.8 bags exact. Wider joints and larger blocks take more — at 4 bags per 100 sq ft the same wall needs 6.4 bags exact, a whole third more, from one label figure. Check the label before multiplying, not after ordering: the bag rate is the input people assume instead of reading, and the assumption is what under-orders.
Step 4: Add waste for spillage
Mortar is dropped, re-tempered and buttered, so add waste before ordering: 10% for a straight run takes 4.8 bags to 5.28. A first-time layer, or a wall with many corners and piers, wants 15%, which would take the same wall to 5.52 bags before rounding. Waste is not spare stock — it is the mortar the job consumes in dropping and re-tempering, and a wall ordered without it runs dry before the last course, with the merchant closed and the wall open.
Step 5: Order whole bags, and count the extras
Order 6 bags, since mortar is sold by the bag and 5.28 rounds up, not down. Then count what bags do not cover: the bricks themselves, the sand and cement if you mix your own, the water, and the tools — none of these come in the bag count. Keep one spare bag after the job: it patches a cracked joint, and a matching batch may not exist next year.
Mortar in numbers
Suppose the wall is 20 ft by 8 ft, at 3 bags per 100 sq ft, with 10% waste. Area: 20 × 8 = 160 sq ft. Hundreds: 160 ÷ 100 = 1.6. Bags exact: 1.6 × 3 = 4.8. With waste: 4.8 × 1.10 = 5.28, rounded up to 6 bags. Order: 6 bags, plus bricks bought separately.
Common mistakes
The most common mistake is measuring the wall gross and forgetting the openings, which over-orders by exactly the opening area. The second is assuming 3 bags per 100 sq ft without reading the label, when wide joints take 4. The third is skipping the waste allowance, which under-orders by exactly the amount the dropping and re-tempering consume. The fourth is counting the bricks as mortar, which are bought by the piece and counted separately. The fifth is rounding down instead of up, which orders a wall short by the last course.
Worked example, start to finish
A wall, 20 ft by 8 ft, 3 bags per 100 sq ft, 10% waste. Area: 160 sq ft. Hundreds: 1.6. Bags exact: 4.8. With waste: 5.28, rounded up to 6 bags. Result: order 6 bags, plus bricks bought separately, and keep one spare bag for joint repairs. If the same wall used 4 bags per 100 sq ft instead, the exact count would be 6.4 bags and the order 8 with waste — the bag rate alone would add 2 bags, which is why step three, reading the label, matters most.
What changes the answer most
The bags-per-100-sq-ft figure changes the answer most: moving from 3 to 4 adds a third to the whole order at a stroke, since it multiplies every hundred square feet. The wall size is second: length and height move the area, but only across a bag rounding does the shop list change. The waste allowance is third: 10% is small beside the bag rate, but it is the difference between a finished top course and an open one. The openings are fourth, and they change only the measured area, never the formula. If the budget is tight, build a shorter wall before cutting the waste allowance.
Frequently asked questions
How many bags of mortar do I need for a 20×8 wall?
6 bags at 3 per 100 sq ft with 10% waste. The wall is 160 sq ft; 160 ÷ 100 × 3 = 4.8 bags exact, and waste takes it to 5.28, rounded up to 6.
What does bags per 100 sq ft mean?
How many mortar bags cover 100 sq ft of wall face. This guide uses 3 for a standard brick wall; wide joints and large blocks need more, so check the bag label.
Should I subtract door and window openings?
Yes — an opening is wall that is never mortared. Measure the wall gross, subtract each opening, and work from the net area, or the count over-orders.
How much waste should I add to a mortar order?
10% for a straight run laid by an experienced hand, 15% for a first-time layer or a wall with many corners and piers. Waste is the spillage and re-tempering, not spare stock.
Does the mortar count include the bricks?
No — this guide counts mortar bags only. The brick calculator counts the bricks for the same wall, and the mortar calculator repeats the maths live.
Pre-mixed bags or mix my own mortar?
Pre-mixed bags suit small walls: the count here is bags. For a long wall, sand plus cement can cost less per square foot, but the bag count still sizes the job — convert bags to volume before pricing bulk.